Construction of the Dehydrated Sludge Temporary Storage Yard, with the following sequence of works:

- Construction of temporary diversions and removal of pipework and infrastructure within the work footprint
- General earthworks
- Construction of in-situ reinforced concrete elements
- Installation of prestressed concrete elements
- Installation of roofing and façade elements (lateral protection on the north façade)
- Installation of technical channel, pipework and reformulation of the polyelectrolyte injection system
- Construction of electrical infrastructure and electromechanical installations
- Installation of irrigation system
- Construction of road accesses
- Topsoil spreading and lawn seeding